Home »opinion »columns »Update on Strandherd-Armstrong...
  • Small - Large
  • |
  • Print
  • |
  • Email
  • |
  • |
  • Pierre Poilievre
  • |
  • Jan 11, 2011 - 10:56 AM
  • |
  • |
  • Report a Typo or Correction

Update on Strandherd-Armstrong Bridge

This week I joined City of Ottawa officials to discuss progress on the Strandherd-Armstrong Bridge construction. The federal government is funding one third of the cost of the bridge and as your federal representative, I am pleased to share with you some of the developments on the project.

First, you will be happy to learn that the project is on time and on budget. That means it will be done by 2012 and should cost slightly less than the original projection of $48 million. To date about $6 million in funds have been expended and the project is about 12% complete by the measure of dollars spent. About 60% of the site preparation is done, 100% of the footing for deep foundations on the east side is complete, the bridge launching system is 55% done and the fabrication of the structural steel is 25% finished. The on-site bridge construction is expected to begin in April of 2011 and the bridge platform should be launched into place by October 2011.

Government approvals for the construction have also moved rapidly. The Rideau Valley Conservation Authority, National Capital Commission, and the Algonquin of Ontario have all given full approvals for the construction. Parks and Transport Canada are reviewing proposed temporary in-river installations as we speak and I am working with those departments to ensure that approvals proceed promptly.

Second, the size and scope of the bridge is impressive. It will contain four lanes for cars and trucks, two for buses, two for bikes, two for turning and two sidewalks. It will be 143 meters long and 50 meters wide. The top of the main arch, which will support the structure with cables from above, will be about 31 meters high—that is about 10 storeys!

Third, without the construction of additional lanes on Earl Armstrong Road there would be a bottleneck of cars entering and leaving the bridge. Under Canada’s Economic Action Plan, I was pleased to secure federal funds to cover a third of the cost of adding new lanes. There had been some difficulty in completing this project by the Action Plan’s March deadline, putting some of the funding in peril, however, Prime Minister Harper has now announced an extension until October allowing for an additional construction season to complete it. 

I will continue to work with the city and the province, in order to see this project through to fruition. It is my top priority and the community’s most important project.

As always, if you have a questions or suggestions, contact me through my website resultsforyou.ca or by phone 613 990-4300.



  • Small - Large
  • |
  • Print
  • |
  • Email
  • |
  • |
More Stories
Featured
Old favourites, new twists set for Hintonburg ArtsPark
KRISTY STRAUSS | May 14

Old favourites, new twists set for Hintonburg ArtsPark

HINTONBURG - Hintonburg’s Parkdale Market will be celebrating the arts once...